WI #99
BI Beam Replacement - for Balcony that is leaning
Status:
New
Priority:
Medium
Assignee:
-
Category:
-
Start date:
04/12/2026
Due date:
% Done:
0%
Estimated time:
Description
Beams Project:
8 beams 2x12x8 Beams
1/2 Plywood + Glue to Sandwich
Stucco Paper + Wire
45 Joist hangers 2x6?
Hanger Nails
hex heads - wood screws 4" - metal plates U 4 columns - so total of 18
3" nails -
4x4 type wood to prop up - doing 16' sections.
Framing nails 21 degrees - 16 penny
Structural repair Permit will be required since load bearing.
Elastomeric, More Portland Cement