PSS #84
Updated by Sieu Ngo 20 days ago
Things to verify w/ Brandy that they are complete...
# Roof Leak - above 208
# roofing DC 200
# 123 109 - secured counter and piping underneath
# removing fence stakes ceiling - need update - we giving up or we done?
# Waterproof the stragglers .. putting room back circuit - need pic from brandi
Medium Priority togeher.
# white speed queen washer
# Brandy - arrange for rocks to be moved from PSS - get running - Wyatt BI to DC
# Gas Dryer 123 - install ignitor once arrive on 29th - Wyatt secured counter and piping underneath
# Brandy take care of weeds - wrap up on parking lot +need weed eater+ - including painting the short side first, then the extra curbing for "new row" - can line out w/ railroad ties.
# Wyatt - Dryer from SJ - coin machine - that is now at DC - DRILL Out Lock need key for coinbox
# additional parking curb - releaser..
# 200 - get required part, use to fix PSS electrical dryer move in ready ... paint, bathroom, + doors+ propane heater hook up
# Schedule Room to Room inspection.. Need Melissa, ptac/fart fan cleaning .. check mice/pest/dogs and list ALL angle Turnoffs that need check list.. https://docs.google.com/document/d/1JpF8vhnsACoaNJxllpKnA3YexxxIPXxH3fPEHqpOrzo/edit?usp=sharing replacement
# removing fence stakes - +need jack+
# drywall sag - 2nd floor balcony ceiling - need fixed up and +drywall+ ?.. also better cable management managment
# Main Sign - need better lights.
# Secure corner post and Put up No Semi Truck sign
- need screws
# put in sink in laundry room - need faucet hooked up - Paul faucets, base
# Remove curbing, old staircase on Short Side - Post inserted, for "Compact Car Sign" jackhammer
# Getting remaining lights downstairs, where joey cut the line, working again.
# Continue selling unneeded equipment - such as all the old flat tv (not smart ones!!)
Priority Items:
# 200 - get move in ready (Paul).. carpet arriving 5/26
# Clean up the bar area - organize what no longer belongs (Brandy/Marlene)
# Start on Bar since SJ has had better luck w/ selling TV's at full price, lets get 2 or 3 up there
Waterproof the back circuit by L2 that Ben installed w/out permission
Move swamp cooler to back of building behind bar
Main sign - convert doesn't light up at night, looks terrible after Ben/Art tried 4 different times, including putting my extra bright lightbulbs.. will eventually have to dorm style resolve.
Figure out where the hell joey cut the wire that stopped downstairs light from working
# snow blower - Paul - see #112
sell electric unit
Old Notes
# DC THNN wire #10 for lines installed in back
# snow blower - sell electric unit
# Roof Leak - above 208
# roofing DC 200
# 123 109 - secured counter and piping underneath
# removing fence stakes ceiling - need update - we giving up or we done?
# Waterproof the stragglers .. putting room back circuit - need pic from brandi
Medium Priority togeher.
# white speed queen washer
# Brandy - arrange for rocks to be moved from PSS - get running - Wyatt BI to DC
# Gas Dryer 123 - install ignitor once arrive on 29th - Wyatt secured counter and piping underneath
# Brandy take care of weeds - wrap up on parking lot +need weed eater+ - including painting the short side first, then the extra curbing for "new row" - can line out w/ railroad ties.
# Wyatt - Dryer from SJ - coin machine - that is now at DC - DRILL Out Lock need key for coinbox
# additional parking curb - releaser..
# 200 - get required part, use to fix PSS electrical dryer move in ready ... paint, bathroom, + doors+ propane heater hook up
# Schedule Room to Room inspection.. Need Melissa, ptac/fart fan cleaning .. check mice/pest/dogs and list ALL angle Turnoffs that need check list.. https://docs.google.com/document/d/1JpF8vhnsACoaNJxllpKnA3YexxxIPXxH3fPEHqpOrzo/edit?usp=sharing replacement
# removing fence stakes - +need jack+
# drywall sag - 2nd floor balcony ceiling - need fixed up and +drywall+ ?.. also better cable management managment
# Main Sign - need better lights.
# Secure corner post and Put up No Semi Truck sign
- need screws
# put in sink in laundry room - need faucet hooked up - Paul faucets, base
# Remove curbing, old staircase on Short Side - Post inserted, for "Compact Car Sign" jackhammer
# Getting remaining lights downstairs, where joey cut the line, working again.
# Continue selling unneeded equipment - such as all the old flat tv (not smart ones!!)
Priority Items:
# 200 - get move in ready (Paul).. carpet arriving 5/26
# Clean up the bar area - organize what no longer belongs (Brandy/Marlene)
# Start on Bar since SJ has had better luck w/ selling TV's at full price, lets get 2 or 3 up there
Waterproof the back circuit by L2 that Ben installed w/out permission
Move swamp cooler to back of building behind bar
Main sign - convert doesn't light up at night, looks terrible after Ben/Art tried 4 different times, including putting my extra bright lightbulbs.. will eventually have to dorm style resolve.
Figure out where the hell joey cut the wire that stopped downstairs light from working
# snow blower - Paul - see #112
sell electric unit
Old Notes
# DC THNN wire #10 for lines installed in back
# snow blower - sell electric unit